The Parts of a New Deck
For deck installation in Fort Collins or nearby, Fort Collins Deck Contractors can build your new deck from pressure-treated wood, cedar or composite.
What a new deck includes
- Concrete footings, set below the frost line when the deck fastens to the house
- The frame: posts, beams and the joists the boards sit on
- A ledger, the board that ties the frame to the house, on an attached deck
- Deck boards in pressure-treated wood, cedar or composite
- Stairs down to the yard, where the deck needs them
- Railing along the open sides, where the deck needs it or you'd like it
Attached to the House or Standing on Its Own
An attached deck is fastened to the house with a ledger and stands on footings out at its far edge. It's the kind you step onto straight from the back door. In Fort Collins, an attached deck needs a city permit at any height, even when it sits a step off the ground.
A freestanding deck holds itself up on footings all the way around and doesn't touch the house, so it can sit out in the yard or near a tree. Its footings don't have to go as deep, and only a small, low deck standing on its own can skip the city's permit.
Which one suits your yard comes down to where you'd like to sit and what's on that side of the house.
Things on the Back of the House That Change the Plan
A basement window under the deck. If the deck will cover the well of a basement escape window, Fort Collins asks for enough clear room between the top of the well and the underside of the deck for the window to still work as a way out. We lay out the frame around it.
A bay window or a bump-out. When the deck would fasten to a part of the house that hangs out past the foundation, like a bay window, the city asks for engineered plans for how it attaches. We look at that wall early, so it's part of the plan and the price from the start.

A back door up on the second floor. A deck that high stands on tall posts and needs a long staircase to reach the yard, with railing along every open side and down the stairs.
Stairs and Railing on a New Deck
When a deck needs railing. Fort Collins asks for a guard where a deck sits 30 inches or more above the ground, measured three feet out from its edge. A deck that stays lower than that can go without one, if you'd rather keep the edge open.
Where the stairs land. The city asks for a solid, level landing at the top and bottom of deck stairs, such as flagstone or concrete, so the last step doesn't come down onto the lawn.
A light at the top of the stairs. Deck stairs need one, and in Fort Collins a new one must be shielded and point down at the steps, the dark-sky kind, which keeps the light where you're walking.
Picking Your Deck Boards
On a new deck, you pick the boards you walk on and the railing around them: pressure-treated wood, cedar, or composite decking, which a lot of people call Trex. If you can't decide, we can price your deck both ways.
Some parts of Fort Collins fall inside the state's wildfire map, where the wildfire code can reach the deck boards. We check what applies to your house before the boards are picked.
New Railing or Stairs for the Deck You Have
If the frame and boards on your deck are in good shape and it's the railing you've grown tired of, a new railing can go on by itself, and so can a second staircase to the yard.
Sometimes a railing only has a few loose pieces, and fixing those is a smaller job than a new one. If a repair will do, we'll tell you. In Fort Collins, replacing the railing or the stairs on a deck takes a permit.